Timeline of Important
Events for your Sunroom |
|
|
|
|
|
|
|
|
|
|
Additional Time |
|
|
|
|
Event |
Accumulated |
for Special |
|
|
|
| EVENT |
Time |
Time |
Circumstances |
|
Description of Event and
Procedures |
|
|
|
|
|
|
|
|
|
|
|
|
|
| SALE |
|
1 day |
1 day |
- |
You will sign paperwork
for the construction of your sunroom. |
|
|
|
|
|
|
| PAPERWORK |
1 day |
2 days |
|
Patterson Sales Rep will
bring your contract to our office the morning |
|
|
|
| |
|
|
|
|
after the paperwork has
been signed to begin processing. |
|
|
|
|
|
|
|
| FINANCING
AND VERIFICATION OF FUNDS |
|
|
Typically, our financing
department will be able to provide you with the terms |
|
|
| |
(1) Financing Through Patterson |
1-2 days Ave. |
2-4 days |
1-2 weeks |
of the financing on the
day after the sale. In some cases, we
may work with |
|
|
| |
|
For loan Approval |
from sale |
for consolidation |
additional lenders and
this may take an extra day or two. A
consolidation loan |
|
|
| |
|
1-3 weeks to |
|
loan |
may take longer for
approval. Once you agree to the terms
of the loan, costs |
|
|
| |
|
loan signout |
|
begin to incur on the job
with respect to permitting, remeasuring, etc.. |
|
|
|
| |
|
|
|
|
|
| |
(2) Cash Sales |
3 days |
5 days |
|
Within 2-3 days, our
financing department will have verified your funds with |
|
|
| |
|
|
from sale |
|
the bank on cash sales. |
|
|
|
| |
|
|
|
|
|
| |
(3) Obtaining Your Own Financing |
Varies |
Varies |
Varies |
We
will verify your funds prior to the starting
work on the job, we will wave |
|
|
| |
|
|
|
|
this requirement if you
agree to accept our financing as backup to your own. |
|
|
|
|
|
| HOMEOWNERS
ASSOCIATION (HOA) |
1 to 4 |
2 to 4 |
+2 weeks for |
Following approval of
your financing or cash verification, we will submit your |
|
|
| |
APPROVAL |
weeks |
weeks from |
Architectural |
application
drawings (and required survey) to your homeowner's management |
|
|
| |
(Where applicable) |
|
loan approval |
Review |
association company for
their review. Depending on the
frequency of |
|
|
|
| |
|
|
Approval |
the HOA meetings, an
approval can take 1-4 weeks.
Additionally, some |
|
|
| |
|
|
HOA's require
architectural review approval. You
will receive a courtesy call |
|
|
| |
|
|
from our office upon HOA
approval. If the homeowner's
association contacts |
|
|
| |
|
|
|
|
you directly with the
approval, please call our office as soon as possible. |
|
|
|
|
|
| COMPUTER
AIDED DESIGN (CAD) |
1 Week |
1 to 2 |
Up to 1 week |
Following approval of
your financing or cash verification, we will create |
|
|
|
| AND ENGINEERING |
|
weeks from |
in high volume |
CAD
drawings and engineer your sunroom.
In peak sale months of the year it |
|
|
| |
|
|
loan approval |
months |
may take and additional
week for this process due to backlog. |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| PROJECT
MANAGER VISIT |
1 to 3 days |
1 to 2 |
|
Within 1-3 days of receiving CAD drawings and
engineering a project manage |
|
|
| |
|
following |
weeks |
|
will call to schedule aa
meeting with you at ;your home to verify measurements, |
|
|
| |
|
CAD Drawings |
from loan |
|
review time flows and
schecduling. |
|
|
|
| |
|
of job |
approval |
|
Our project manager will
call you to schedule and appointment between |
|
|
| |
|
|
|
|
8 am - 5 pm Monday -
Friday. |
|
|
|
|
|
|
|
|
|
| PERMITS |
|
1 to 3 |
2 to 5 |
+1 to 3 weeks |
Following approval of
your financing or cash verification, we will also |
|
|
|
| |
|
weeks |
weeks from |
in St. Johns Co. |
apply for permitting of
your job. Permitting time varies with
each municipality. |
|
|
| |
|
|
loan approval |
because HOA |
St. Johns and Nassau
counties take longer to receive permits.
Also, |
|
|
|
| |
|
|
Duval, Clay |
approval needed |
St. Johns County will NOT
accept permit application until the HOA is approved. |
|
|
| |
|
|
before permit |
Upon receipt, the permit
must be posted near the job so it is visible to city |
|
|
| |
|
|
Up to 5 to 10 |
submitted |
inspectors until the point in time
when all inspections (including final |
|
|
|
| |
|
|
weeks for St. Johns |
|
inspection) have passed. Our office will call you upon receipt of
permits. |
|
|
|
| |
|
|
or Nassau Counties |
|
|
|
|
|
|
|
|
|
|
|
|
| LEGAL
BOUNDARY SURVEY |
None, if |
|
2 - 4 weeks |
All municipalities
require a Legal Boundary Survey for permits. |
|
|
| |
* If required, must have before |
homeowner |
|
if we order |
We request a copy of your
survey within 3 business days from the |
|
|
| |
submittal of permit |
has legal |
|
new survey |
date of the signed
contract. In absence of a copy of your
survey, |
|
|
|
|
| |
|
boundary |
|
our standard policy is to
order a copy of the survey at a cost to you |
|
|
| |
|
survey |
|
of approximately $300
(for a subdivision lot). Rural
properties with |
|
|
| |
|
|
additional acreage will
cost significantly more. This can add
2-4 |
|
|
| |
|
|
weeks to the permitting
process if we must order the survey. |
|
|
| |
|
|
|
|
The Legal Boundary Survey
is required prior to ordering the permit. |
|
|
|
| |
|
|
|
|
|
| SEPTIC
TANK PUMPOUT |
None, if |
|
3-10 days |
Some municipalities
require proof that your septic tank has been pumped |
|
|
| |
* If required, must have before |
homeowner has |
|
from loan approval |
out within the last
year. Your drain field may also need
to be enlarged. |
|
|
|
| |
submittal of permit |
proof of pumpout |
|
As
the owner of the property, you are responsible for these expenses if
they |
|
|
| |
|
within 1 year. |
|
have not been done. In certain situations, we will order the
pump out and will |
|
|
| |
|
3-10 days if new |
|
require reimbursement
from you. This must also be completed
prior to |
|
|
|
| |
|
pumpout ordered. |
|
|
ordering the permit. |
|
|
|
|
|
|
|
|
|
|
| GENERAL
CONSTRUCTION AND PRIOR TO CONSTRUCTION ISSUES |
|
|
|
|
|
|
|
|
|
| |
(1) Prior to Construction |
- |
4 - 8 |
See items |
If your job does NOT
experience delays in financing or permitting, you can |
|
|
| |
(What to expect before construction |
|
weeks |
above |
expect a period of
approximately 4-8 weeks where no work is being performed |
|
|
| |
actually begins on your property) |
|
on your property. However, many things are happening behind
the scenes. |
|
|
| |
|
|
Remeasuring, permitting,
HOA approvals, CAD drawings, and room ordering |
|
|
| |
|
|
are the processes
occurring during this time. |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
| GENERAL
CONSTRUCTION AND PRIOR TO CONSTRUCTION ISSUES (cont) |
|
|
|
|
|
|
|
|
|
| |
(2) Plants and Shrubbery |
2 - 3 |
- |
- |
Please relocate any
plants within the first few weeks after you sign the sales |
|
|
| |
(Please handle prior to construction) |
days |
|
agreement for your
sunroom. We are not responsible for
damage to any trees, |
|
|
| |
|
|
shrubs, flowers, turf or
other plants located within or near the construction zone. |
|
|
| |
|
|
Occaisonally, minor
damage may occur to your grass, particularly during the |
|
|
| |
|
|
construction of the
foundation. The degree to which the
grass is damaged |
|
|
| |
|
|
depends upon current
rainfall, the water table and the amount and type of |
|
|
| |
|
|
equipment required to
build your particular job. Also,
unless noted in the |
|
|
| |
|
|
agreement, it is your
responsibility to remove any trees and stumps (some are |
|
|
| |
|
|
hidden) from the access
area. These
unforseen expenses are not |
|
|
|
| |
|
|
covered in the general
contract. |
|
|
|
| |
|
|
|
|
|
| |
(3) Sprinklers and
Underground Utilities/Obstacles |
|
Our crews can cap your
sprinkler heads, although it is helpful it you can mark |
|
|
| |
(Please handle prior to construction) |
1 - 2 |
|
the sprinklers
beforehand. Moving, replacing or
re-directing your sprinklers |
|
|
| |
|
days |
|
will require the
expertise of a sprinkler company. Keep in mind that sprinkler |
|
|
| |
|
|
repairs should be
completed AFTER the completion of the sunroom. |
|
|
|
| |
|
|
Occasionally during
excavation of the foundation, unforseen items such as |
|
|
| |
|
|
electric lines, septic
tanks, piping, stumps, concrete or other unforseen |
|
|
|
| |
|
|
obstacles could be
encountered which may need to be removed.
These |
|
|
| |
|
|
unforseen expenses are
not covered in the general contract. |
|
|
|
| |
|
|
|
|
|
| |
(4) Yard Access |
- |
- |
- |
It is your responsibility
to leave all gates unlocked and secure all pets during |
|
|
| |
(General Construction Issue) |
|
all
phases of construction of your sunroom.
Please do not leave children |
|
|
| |
|
|
access to the construction area as hazordous
conditions may exist. Your |
|
|
| |
|
|
property will be a
construction site and should be treated as such at all times. |
|
|
| |
|
|
|
|
We are not responisble
for gates which may have not been closed by our crews. |
|
|
|
|
|
| DEMOLITION/TEAR
OUT |
1 - 3 |
|
- |
If a demolition of your
existing room is occurring, please be sure to completely |
|
|
| |
|
days |
|
clear the room of all
items (furniture and plants). Any
items you wish to save |
|
|
| |
|
|
should be removed prior
to the demolition and tear out. We are
not responsible |
|
|
| |
|
|
|
|
for damage to any
existing items. |
|
|
|
|
|
|
|
|
|
| FOUNDATION |
1 - 3 |
1 - 10 days |
1 week |
The concrete crew will
commence work on the foundation upon completion of |
|
|
| |
|
days |
following |
for inclement |
permitting as well as
financing and homeowner's association approvals. |
|
|
| |
|
|
HOA Approval |
weather or |
You will receive a
courtesy call when your foundation is ready to be poured. |
|
|
| |
|
|
and Permitting |
material |
The concrete crew will
schedule an approximate time,
however, keep in mind |
|
|
| |
|
|
availability |
that these times may
vary. Weather, material availability
and job size often |
|
|
| |
|
|
affect our ability to
determine when we will be able to schedule the concrete. |
|
|
| |
|
|
Foundation Schedule: The
crew will form the job on the first day.
In some |
|
|
| |
|
|
counties the forms may
need to be inspected prior to pouring the concrete. |
|
|
| |
|
|
The final step is the
pouring of the concrete, weather permitting.
Small cracks |
|
|
| |
|
|
occurring in the slab are
normal. Please call our office if you
experience cracks |
|
|
| |
|
|
|
|
larger than 1/8" (or
if you can stand a nickel in the crack). |
|
|
|
|
|
|
|
| PRE-TREATMENT
OF |
1 |
1 - 3 days |
- |
Pest control treatment is
a code requirement. It is our standard
procedure to |
|
|
| |
CONCRETE SLAB |
day |
following |
|
use our own pest control
company. If you elect to use your own
pest company |
|
|
| |
|
|
concrete pour |
|
to spray the slab, we
must be notified of this in advance and a time must be |
|
|
| |
|
|
coordinated for the
spraying the day before the concrete is poured. If you elect |
|
|
| |
|
|
to have your own pest
control company pretreat the slab, we will credit you $75. |
|
|
| |
|
|
Keep in mind that you may
pay as much as $200-$300 from your own company |
|
|
| |
|
|
|
|
for this service. Do not forward the bill to us. You are responsible for this cost. |
|
|
|
|
|
| SUNROOM
CONSTRUCTION |
|
|
|
|
|
|
|
|
|
|
|
| |
(1) Build Room |
3 - 5 |
0 - 4 |
- |
Approximately 1-4 weeks
following the completion of the foundation, your |
|
|
| |
|
days |
weeks from |
|
sunroom will be delivered
to our office. You will be notified by
our production |
|
|
| |
|
|
concrete |
|
coordinator to schedule
the installation of the sunroom.
Installations normally |
|
|
| |
|
|
take 3-5 days. |
|
|
|
| |
|
|
|
|
|
| |
(2) Custom Processes |
|
|
|
|
| |
(A) Custom Transom Glass |
|
7 - 10 days |
After
the room is built we will measure openings and have glass custom made, |
|
|
| |
|
|
this will take upwards of
10 days because the glass is tempered. |
|
|
|
| |
(B) Shingled Roof |
|
14 + days |
Typically,
we will have a roofing subcontractor install shingles which requires us
to |
|
|
| |
|
|
be worked into the
roofers schedule. |
|
|
|
| |
(C) Brick or Stucco Kneewall |
|
14 + days |
This process will also
require subcontractor, and since it is a small job they will |
|
|
| |
|
|
|
|
work the job inbetween
larger jobs. |
|
|
|
|
|
|
|
|
|
| ELECTRIC
AND FLOORING |
1 - 3 |
0 - 2 weeks |
- |
The electric and flooring
will be scheduled approximately 1 - 2 weeks following |
|
|
| |
|
days |
following Room |
|
the erection of your
sunroom. You must
be present for the installation |
|
|
|
| |
|
|
Erection |
|
of the electric so we can
access your electrical panel and circuit |
|
|
| |
|
|
breaker. Prior to this
installation, you should purchase a hugger fan |
|
|
| |
|
|
(a fan without a stem)
and a small door light. This light
will be mounted on the |
|
|
| |
|
|
wall outside of the
door. Please
review your contract at this time |
|
|
|
| |
|
|
regarding electrical
installation. You must contract with
the |
|
|
|
| |
|
|
electrical
crew for any additional work, which would include |
|
|
|
| |
|
|
circuits
for hot tubs, space heaters or airconditioners. |
|
|
|
| |
|
|
Items such as these
require dedicated circuits |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| WALK-THRU |
1 Hour |
At the time the installer |
- |
The crew leader will
request your presence on the job at the completion |
|
|
|
| |
|
|
puts up the room |
|
of the room erection
state for a walk-thru. The purpose of
the |
|
|
|
| |
|
|
walk-thru is for you and
the crew leader to inspect the job thoroughly. If you |
|
|
| |
|
|
or |
|
have any concerns, please
bring them up during the walk-thru. The crew will |
|
|
| |
|
|
normally NOT return to
the job after the walk-thru. If you
have any |
|
|
| |
|
|
at the time the |
|
concerns, please address
them with the crew at such time. The |
|
|
| |
|
|
custom glass is installed |
|
crew
leader will also contact one of our project managers with the purpose of |
|
|
| |
|
|
|
|
creating a
"punchlist" of any items which may need to be completed. |
|
|
|
|
|
|
| Total
Time to Complete Job |
|
10-15 weeks |
|
Many
factors affect the total length of time it takes to complete a job however |
|
|
| |
|
|
on average |
|
length
of time for jobs in Duval or Clay counties is 10-12 weeks after
financing |
|
|
| |
|
|
however, it varies |
|
is secured.
Surveys, custom work such as shingles, stucco, block foundations |
|
|
| |
|
|
from job to job |
|
can
each add 1-2 weeks. Summer rains and
hurricanes can in some years can |
|
|
| |
|
|
|
|
sifnificantly delay
production schedules. |
|
|
|
|
|
|
|
|
| INSPECTIONS |
|
|
|
|
Electrical |
|
|
|
|
|
|
|
| |
|
|
Most municipalities do
not require you to be present.
Exceptions are Duval County, |
|
|
| |
|
|
Flagler
County and City of Palm Coast. You
will be required to be present from the |
|
| |
|
|
hours
of 8 to 5. Inspectors do not normally
tell you when they will show up between |
|
| |
|
|
these
hours. Duval County has a website
(COJ.NET), which has the schedule of |
|
|
| |
|
|
inspections
for the day and gives some idea of timeframes of inspections. |
|
|
| |
|
|
Please remember PHI has
no control over inspectors or timing |
|
|
| |
|
|
of inspections. |
|
|
|
| |
|
|
Final Inspection |
|
|
|
| |
|
|
You
do not need to be present, but inspector must have access to your
backyard |
|
|
| |
|
|
|
|
and
sunroom. Some inspectors will not
enter a fenced backyard if a dog is unleashed |
|
|
|
|
| REVIEW
OF TIMES HOMEOWNER MUST BE PRESENT ON THE JOB |
|
|
|
|
|
|
|
|
|
|
| |
|
|
1. |
Engineering Remeasure and
Contract Review. |
|
|
|
| |
|
|
2. |
Electrical
Installation. Duval Count requires
someone present for electrical |
|
|
| |
|
|
|
inspection also. |
|
|
|
| |
|
|
|
3. |
Walk-thru following
completion of sunroom. |
|
|
|
|
|
|
|
|
| PAYMENT
SCHEDULE FOR FINANCED JOBS |
|
|
|
|
|
|
|
|
|
|
|
| |
Cash |
|
|
Key Funding |
|
GE |
|
|
|
| |
10% Down Payment |
|
|
Homeowner holds
checks until each |
|
Payments are deposited directly to Patterson |
|
|
|
| |
30% due at time of
order or PCC meeting |
|
|
of the following
steps are completed: |
|
on the following schedule: |
|
|
|
| |
50% Upon Room Construction |
|
|
30% Upon Foundation |
|
40% Loan Funding |
|
|
|
| |
10% Upon Job Completion |
|
|
60% Room Construction |
|
50% Room Construction |
|
|
|
| |
|
|
|
10% Job Completion |
|
|
10% Room Completion |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|